Project Progress - July 2011
Bioreactor 4 Bioreactor 4 began construction in January 2009. Civil construction was completed in February 2010, and mechanical and electrical fit-out is almost complete. Bioreactor 4 was commissioned for service in April 2011.
Clarifier 4 Clarifier 4 began construction in Janury 2009 and was commissioned for service in February 2010.
Bioreactors 1-3 Upgrade Once Bioreactor 4 is commissioned, it is proposed to upgrade the existing Bioreactors. This work is anticipated to begin around October 2011, with an installation period of approximately 1 year.
Interstage Pump Stage
The Interstage Pump Station capacity upgrade was completed and commissioned in September 2009.
UV Treatment The UV Treatment capacity upgrade was completed and commissioned in June 2009.
Chemical Dosing
The chemical dosing facility for Phosphorous removal has been installed, and will be commissioned by December 2010.
Solid Stream Upgrade The Solid Stream Upgrade involves a number of work packages and is envisaged to provide significant benefits to the WWTP Solids Treatment process. We are currently the reviewing options for the solid stream upgrade, with a view of confirming options and designs in late 2011. |