Table of Contents |
|
|
Part 1: General |
|
Part 1 |
General Information |
| Checklist 1.1 |
Final Site Inspection & Release |
| Checklist 1.2 |
Pre-Construction Meeting |
|
Part 2: Earthworks
|
| Part 2 |
Earthworks |
| Checklist 2.1 |
Geotechnical Assessment - Scheme Plan approval |
| Checklist 2.2 |
Geotechnical Assessment - Completion of Earthworks |
|
Part 3: Roading
|
| Part 3 |
Roading |
| Checklist 3.1 |
Imported Subgrade |
| Checklist 3.2 |
Subgrade Shape and Relative Height |
| Checklist 3.3 |
Sub-Base Compaction |
| Checklist 3.4 |
Sub-Base Shape and Relative Height |
| Checklist 3.5 |
Basecourse Compaction |
|
Part 4 & 5: Stormwater & Wastewater Reticulation
|
| Part 4 & 5 |
Stormwater & Wastewater Reticulation |
| Checklist 4.1 |
Stormwater & Wasterwater Pipe Laying Checklist |
| Checklist 4.2 |
Manhole Checklist |
| Checklist 4.3 |
Trench Backfill Compaction Test Summary |
| Checklist 4.4 |
Catchpit Checklist |
| Checklist 4.5 |
Final Inspection for Stormwater and Wastewater Drainage |
| Checklist 4.6 |
Landscape Engineering Stormwater Device Inspection/Signoff Checklist |
| Checklist 4.7 |
Landscape Engineering Stormwater Device Management Manual Checklist |
|
Part 6: Water Reticulation
|
| Part 6 |
Water Reticulation |
| Checklist 6.1 |
Water Reticulation Pipe Laying Checklist |
| Checklist 6.2 |
Trench Backfill Compaction Test Summary |
| Checklist 6.3 |
Final inspection for Water Reticulation |
|
Part 7: Street Landscaping
|
| Part 7 |
Street Landscaping |
| Checklist 7.1 |
Street Trees & Gardens - Pre-defects Liability Period Inspection |
| Checklist 7.2 |
Final inspection - Street Trees & Gardens |
|
Part 8: Network Utilities
|
| Checklist 8.1 |
Work Clearance from Network Operators |
|
Part 9: Appendices
|
| Appendix 1 |
Notice of Intention to commence Development Works |
| Appendix 2 |
Schedule for Agreed Corrections |
| Appendix 3 |
Compliance Acceptance/Release |
Appendix 4i Appendix 4ii Appendix 4iii |
Certification Upon Completion of Roads, Pipelines and Other Services Producer Statement - Construction Certificate for As-Built Drawings |
|
Appendix 5i Appendix 5ii |
Requirements & Procedures for Legal Documentation for Minor Works Bonds Requirements & Procedures for Legal Documentation |
| Appendix 6 |
Application for Accetance of Water or Drainage Product for use in the HCC Water Supply Area or Drainage District |
| Appendix 7 |
Guidelines for Submission of Digistal Data for Water and Drainage As-Built Plans |
| Appendix 8i |
Subdividers/Developers Tax Invoice/GST Requiremetns/Asset Register |
| Appendix 8ii |
Subdividers/Developers Invoice/Asset Register |